40W201 Wasco Road, Suite D • St. Charles, IL 60175• Ph: 630.587.0470 • Fax: 630.587.0475
 

HOME

CORPORATE

PROJECTS

SERVICES

 

Projects

Current Projects

In Planning

University of Illinois - "Illinois Height Modernization" - Jim McKenzie, PLS

Village of Campton Hills - "Green Infrastructure Plan" - Rob Linke, P.E.

Village of Algonquin - "East Side Sanitary Sewer Study" - Mark Bushnell, P.E.

City of St. Charles - "Water Distribution System Model Update" - Mike Holland, P.E.

In Design

City of Crystal Lake - "Water Treatment Plant #1 Rehabilitation" - Mark Sikora, P.E.

City of Crystal Lake - "Water Treatment Plant #4 Rehabilitation" - Scott Trotter, P.E., BCEE

City of St. Charles - Well #13 VFD Improvements" - Mark Sikora, P.E.

City of West Chicago - "Route 59 Watermain Replacement" - Steve Cieslica, P.E.

DuPage County Public Works - "Vactor Receiving Station" - Scott Trotter, P.E., BCEE

NMWRD - "Darrell Road Interceptor Sewer Phases 1 - 5 " - Steve Cieslica, P.E.

NMWRD - "Route 120 Low Pressure Sewer" - Mark Sikora, P.E.

Village of Bartlett - "Raw Sewage Pump Station Rehabilitation " - Mark Sikora, P.E.

Village of Sugar Grove - "Mallard Point Stormwater Improvements" - Mark Bushnell, P.E.

Yellow Creek Partnership - Yellow Creek Fish Passage" - Freeport, IL - Rob Linke, P.E.

Currently Bidding

City of St. Charles - "Headworks Rehabilitation" - Scott Trotter, P.E., BCEE

 

Under Construction

City of Batavia - "Peg Bond Band Shell" - Mark Bushnell, P.E

DeKalb Sanitary District - "2010 Lining Program" - Mike Holland, P.E.

DeKalb Sanitary District - "2010 Spot Repair Program" - Mike Holland, P.E.

DeKalb Sanitary District - "Moraine Terrace Sanitary Sewer Replacement" - Mark Bushnell, P.E.

Village of Algonquin - WWTP Site Improvements - Scott Trotter, P.E, BCEE

Village of Union - Public Works Garage - Steve Cieslica, P.E.

 

Project Name: Village of Port Barrington - Low Pressure Sanitary Sewer Phase II

Project Description:

The Village of Port Barrington is using Illinois EPA Low Interest Loan and ARRA funds for installation of a low pressure sewer system including 12,000 lineal feet of low pressure force main ranging in size from 1.25" to 4", seven (7) air release valves, thirteen (13) cleanouts, ninety-three (93) grinder pump units and restoration.

Project Manager: Mark Bushnell, P.E.
Contractor: Mark Cresmary Construction

Contract Value:$1,200,000

 

Project Name: City of St. Charles - Rehabilitation of East Side / Riverside Lift Station

Project Description:

The City of St. Charles will be using Illinois EPA Low Interest Loan and ARRA funds for rehabilitation of East Side and Riverside Lift Station

The proposed improvements  of East Side Lift Station includes conversion of the existing dry pit pump system to a submersible pumping system and replacement of the existing screen.  The project includes demolition of existing equipment and installation of pumps, screens, piping, electrical switch gear and minor exterior piping.  The project also includes minor rehabilitation of the existing building including replacement of doors, roof and painting.

The proposed improvements of Riverside Lift Station include replacement of two mechanical fine screens, minor piping, and installation of a screens washer and breakwater system.

Project Manager: Mike Holland, P.E.
Contractor: Meccon Industries
Contract value: $2,100,000
 

Project Name: DeKalb Sanitary District - Country Club Lift Station

Project Description:

The DeKalb Sanitary District will be using Illinois EPA Low Interest Loan and ARRA funds for construction of Country Club Lift Station Improvements.

The proposed improvements consist primarily of the following:

1. Construction a new lift station and building including wet well, valve room, electrical room, pumps, piping, electrical switch gear, , generator, HVAC and controls system.

2. Removal of the existing lift station and control building

3.Site improvements including underground gravity sewer and forcemain, electrical and roadway improvements.

Project Manager: Mark Sikora , P.E.
Contractor: Williams Brothers Construction
Contract Value: $1,900,000
 

Project Name: DeKalb Sanitary District - Phase 1A Biosolids Rehabilitation Project

Project Description:

The DeKalb Sanitary District will be using Illinois EPA Low Interest Loan and ARRA funds for construction of Phase 1A Biosolids Rehabilitation Project.

The proposed improvements consist primarily of the following:

1. Rehabilitation of the four (4) fifty-five foot diameter anaerobic digesters including replacement of two floating covers, two gas holder covers, mixing systems and piping.

2. Rehabilitation of the forty foot diameter sludge storage tank including a fixed cover, mixing system and piping.

3. Construction of a new Digester Operation Building to house boiler heat exchangers, pumps, piping and controls

4. Construction of a new Sludge Handling Building to include WAS storage, Thickened WAS storage,gravity belt thickeners, centrifuges, conveyors, polymer units, pumps, piping and controls.

5. Construction of 100 by 75 foot dewatered sludge storage building.

Project Manager:Scott Trotter, P.E., BCEE
Contractor: Williams Brothers Construction
Contract Value: $17,750,000

 

 

 

 
 
 
  top of page