University of Illinois - "Illinois Height Modernization" - Jim McKenzie, PLS
Village of Campton Hills - "Green Infrastructure Plan" - Rob Linke, P.E.
Village of Algonquin - "East Side Sanitary Sewer Study" - Mark Bushnell, P.E.
Campton Township - Gray Willows Farm - Rob Linke, P.E.
City of Cystal Lake - WTP#4 Residuals Lift Station and Forcemain - Mark Sikora, P.E.
City of Harvard - WTP#1 UV Disinifection System - Scott Trotter, P.E., BCEE
City of St. Charles - Main WWTP Biosolids and Operation Building - Scott Trotter, P.E., BCEE
City of West Chicago - "Route 59 Watermain Replacement" - Steve Cieslica, P.E.
DuPage County Public Works - "Vactor Receiving Station" - Scott Trotter, P.E., BCEE
DuPage County DOT - "Salt Storage and Supermix Facility"- Scott Trotter, P.E., BCEE
NMWRD - "Darrell Road Interceptor Sewer Phases 1 - 5 " - Steve Cieslica, P.E.
NMWRD - "Route 120 Low Pressure Sewer" - Mark Sikora, P.E.
Village of Bartlett - "Raw Sewage Pump Station Rehabilitation " - Mark Sikora, P.E.
Village of Bartlett - Sludge Dewatering Improvements - Mark Sikora, P.E.
Village of Sugar Grove - "Mallard Point Stormwater Improvements" - Mark Bushnell, P.E.
Yellow Creek Partnership - Yellow Creek Fish Passage" - Freeport, IL - Rob Linke, P.E.
Village of Woodridge - Materail Storage Facility - Mark Bushnell, P.E.
Village of Union - Depot to Washington Watermain Improvements - Steve Cieslica, P.E.
Village of Union - 2011 MFT Improvements - Steve Cieslica, P.E.
Village of Union - Water Treatment Facility Improvments - Scott Trotter, P.E., BCEE
City of St. Charles - Well #13 VFD Improvements
Campton Township - Poyner Park Drainage Improvements - Rob Linke, P.E.
City of Crystal Lake - WTP#4 Ion Exchange Improvements - Mark Sikora, P.E.
City of Crystal Lake - WTP#4 VOC Improvements - Mark Sikora, P.E.
City of Crystal Lake - Water Treatment Plant #1 Rehabilitation - Mark Sikora, P.E.
City of St. Charles - Safety Training Facility - Colin Shulick
City of St. Charles - Main WWTP Headworks Upgrade - Scott Trotter, P.E. BCEE
City of St. Charles - Park Shore Siphon Rehabilitation - Scott Trotter, P.E., BCEE
DeKalb Sanitary District - Phase 1A Biosolids Rehabilitation - Scott Trotter, P.E., BCEE
DeKalb Sanitary Disitrict - Country Club Lift Station - Scott Trotter, P.E., BCEE
DeKalb Sanitary District - Tertiary Filter Rehabilitation - Scott Trotter, P.E., BCEE
Illinois American Water - River Grange Watermain and Sanitary Sewer Replacement - Mark Bushnell, P.E.
NMWRD - Fern and South Shore Lift Station Rehabilitation - Mark Sikora, P.E.
Village of Algonquin - Royal Hill Phase I - Roadway Rehab - Mark Bushnell, P.E.
Village of Algonquin - S. River Road Retaining Wall - Mark Bushnell, P.E.
Village of Warrenville - Williams Court Sewer and Water Extension - Mark Bushnell, P.E.
City of Elgin- Waterford Units 1, 2 & 3 - Steve Cieslica, P.E.
Project Description:
The Village of Port Barrington is using Illinois EPA Low Interest Loan and ARRA funds for installation of a low pressure sewer system including 12,000 lineal feet of low pressure force main ranging in size from 1.25" to 4", seven (7) air release valves, thirteen (13) cleanouts, ninety-three (93) grinder pump units and restoration. |
| Project Manager: Mark Bushnell, P.E. |
| Contractor: Marc Kresmery Construction LLC |
Contract Value:$1,200,000
|
| |
Project Description:
The City of St. Charles will be using Illinois EPA Low Interest Loan and ARRA funds for rehabilitation of East Side and Riverside Lift Station
The proposed improvements of East Side Lift Station includes conversion of the existing dry pit pump system to a submersible pumping system and replacement of the existing screen. The project includes demolition of existing equipment and installation of pumps, screens, piping, electrical switch gear and minor exterior piping. The project also includes minor rehabilitation of the existing building including replacement of doors, roof and painting.
The proposed improvements of Riverside Lift Station include replacement of two mechanical fine screens, minor piping, and installation of a screens washer and breakwater system. |
| Project Manager: Mike Holland, P.E. |
| Contractor: Meccon Industries |
| Contract value: $2,100,000 |
| |
Project Description:
The DeKalb Sanitary District will be using Illinois EPA Low Interest Loan and ARRA funds for construction of Country Club Lift Station Improvements.
The proposed improvements consist primarily of the following:
1. Construction a new lift station and building including wet well, valve room, electrical room, pumps, piping, electrical switch gear, , generator, HVAC and controls system.
2. Removal of the existing lift station and control building
3.Site improvements including underground gravity sewer and forcemain, electrical and roadway improvements. |
| Project Manager: Mark Sikora , P.E. |
| Contractor: Williams Brothers Construction |
| Contract Value: $1,900,000 |
| |
Project Description:
The DeKalb Sanitary District will be using Illinois EPA Low Interest Loan and ARRA funds for construction of Phase 1A Biosolids Rehabilitation Project.
The proposed improvements consist primarily of the following:
1. Rehabilitation of the four (4) fifty-five foot diameter anaerobic digesters including replacement of two floating covers, two gas holder covers, mixing systems and piping.
2. Rehabilitation of the forty foot diameter sludge storage tank including a fixed cover, mixing system and piping.
3. Construction of a new Digester Operation Building to house boiler heat exchangers, pumps, piping and controls
4. Construction of a new Sludge Handling Building to include WAS storage, Thickened WAS storage,gravity belt thickeners, centrifuges, conveyors, polymer units, pumps, piping and controls.
5. Construction of 100 by 75 foot dewatered sludge storage building. |
| Project Manager:Scott Trotter, P.E., BCEE |
| Contractor: Williams Brothers Construction |
| Contract Value: $17,750,000 |
|